Udhampur–Srinagar–
Baramula Rail Link (USBRL)
km
338
Baramulla
Uri (inprogress)
(inprogress)
Kupwara Line (inprogress)
 
Kupwara
Bandipora Line
(proposed)
330
Sopore
323
Hamre
315
Pattan
307
Mazhom
297
Nadigam
292
Budgam
281
Srinagar
275
Pampore
Jhelum Bridge
269
Kakapora
264
Ratnipora
259
Awantipora
252
Panzgom
Shopian Line
(inprogress)
245
Bijbehara
to Pahalgam (inprogress)
238
Anantnag
231
Sadura
226
Qazigund
Hillar Shahabad
208
Banihal
Tunnels T54-T55
Tunnel T53 (2.71 km)
Tunnel T52 (8.61 km)
Khari
Tunnel T51
Tunnel T50 (12.775 km)
Sumber
Tunnel T49 (10.178 km)
Tunnel T48 (2.242 km)
Tunnels T46-T47
Tunnel T45 (2.733 km)
Sangaldan
Tunnel T44 (11.13 km)
Tunnel T43 (6.292 km)
Sawalkote
Tunnel T42 (9.316 km)
Dugga
Tunnel T41 (2.127 km)
Tunnels T38-T40
Tunnel T37 (3.493 km)
Bakkal
Tunnel T36 (5.941 km)
Reasi
Tunnel T35 (3.007 km)
Tunnel T34 (5.098 km)
Tunnel T33 (3.209 km)
Tunnels T31-T32
Shri Mata Vaishno
Devi Katra
Tunnels T26-T30
Tunnel T25 (2.497 km)
62
Chak Rakhwal
Tunnel T24
Tunnel T23 (3.12 km)
Tunnels T21-T22
Bhaderwah Line
(planned)
53
Udhampur
44
Ramnagar
Tunnels T14-T20
Tawi Bridge
22
Manwal
Tunnels T10-T13
14
Sangar
Tunnels T8-T9
Tunnel T7 (2.4 km)
Tunnels T4-T6
10
Bajalta
Tunnels T1-T3
Poonch line
(planned)
0
Jammu Tawi
km

The Anji Khad bridge is a cable-stayed bridge in the Udhampur-Srinagar-Baramulla-Rail-Link (USBRL) in the Jammu Division of Jammu and Kashmir, India. It is widely regarded as an engineering marvel because of its height, the steepness of the sides of the gorge it spans, and its striking design, consisting of an asymmetrical arrangement of cables anchored to a single massive pylon.

The bridge lies south of the Chenab Bridge, near Reasi, where the railway line crosses the deep chasm ('Khad' in Hindi) of the Anji River. It is India's first cable-stayed railway bridge. It has been built by Hindustan Construction Company.

History

Arch Bridge design proposal: rejected

The Anji Khad bridge was initially proposed to be an arch bridge. It was designed as a long steel arches span bridge. Its total length was to be 473 m (1,552 ft), with a main arch span of 265 m (869 ft), and a deck height of 189 m (620 ft). Quality aspects, construction standards, indigenous materials, and the painting scheme were proposed to be similar to the Chenab Bridge. Later, a committee headed by a former railway board chairman recommended that the location was not suitable for an arch bridge. In particular, the unstable geology of the Himalayan mountains combined with the steepness of the sides of the gorge made an arch bridge impractical.[2]

Cable-stayed bridge design proposal: accepted

In October 2016, Indian Railways decided to build a cable-stayed bridge at Anji Khad, [3] with a striking asymmetrical design supported by 96 cables anchored to a single pylon on the Reasi side, of height 193 m from its foundation. [4] The initial cost of the project was set at 458 crore. As per the design, the bridge connects tunnels T34 and T35 on the Katra and Reasi sides respectively. It has a 290 meter main span at a height of 331 m above the riverbed.[5] The main section has a length 473.25 meters out of a total length of over 1,300 meters, with a 120 meter long viaduct.


Construction Site of Anji Khad Bridge - See construction on two hills on extreme left


Status updates

  • January 2017: [ITALFER] to construct cable-stayed Anji Khad Bridge. The work is planned to be completed in 36 months.[6]
  • March 2021: The construction of the single pylon to which the cables will be anchored is completed.[7]
  • April 2023: All 96 cables have been attached, and the bridge stands nearly completed with associated track laying and fine tuning work to be completed in the following few months.[8]
  • August 2023: A trial run was successfully completed.[9]
  • December 2024: In anticipation of the commissioning of the railway line in early 2025, load testing of the bridge was performed, by moving a heavily loaded goods train onto the bridge, along with heavily loaded trucks onto the parallel service roadway on the bridge.
  • January 2025: Speed trials up to 110 kmph were carried out on the bridge on Jan. 8, 2025.

See also

References

No tags for this post.