On 3 May 2021, at 22:22 CDT (UTC−5), a girder overpass in the borough of Tláhuac carrying Line 12 of the Mexico City Metro collapsed beneath a passing train. The overpass, along with the last two railcars of the train, fell onto Avenida Tláhuac near Olivos station, resulting in 26 fatalities and 98 injuries. It was the deadliest accident in the Metro's history in nearly fifty years.
Before the line opened, it faced technical and structural issues that persisted during its operation, resulting in a partial closure of the elevated section where the accident occurred, lasting from 2014 to 2015. An earthquake in 2017 further damaged the structure; although repairs were completed within a few months, residents reported that problems persisted for years. Originally announced in 2007 as an underground line capable of operating rubber-tired trains due to the instability of the city's soil. However, budget and time constraints led to modifications that allowed underground and above-ground operation with steel-wheeled trains. The construction was carried out by Empresas ICA, in partnership with Alstom Mexicana and Grupo Carso, the latter owned by businessman Carlos Slim.
Claudia Sheinbaum, the head of government of the city at the time of the collapse, hired the Norwegian risk management firm Det Norske Veritas (DNV) to investigate the causes of the event. Preliminary findings linked the accident to bridge construction deficiencies, including a lack of functional studs and faulty welds, fatiguing the collapsed beam. Researchers have identified the design change as a factor in track instability and damage since the line commenced operations. Further investigations concluded that the bridge had been designed and built without adhering to quality standards, that the line's construction and design changes had been inadequately supervised, and that there were insufficient fixing and safety elements. Additionally, it was found that periodic maintenance checks, which could have detected the girder buckling, had not been conducted—a claim contested by the city government.
Carso denied any wrongdoing; however, Slim agreed with the Mexican government to repair the section at no cost. In December 2021, the city's attorney general's office filed charges against ten former officials involved in the construction and supervision of the project, including the project director. As of February 2025, they were awaiting trial for manslaughter, injury, and property damage. The bridge was rebuilt, the sections constructed by Carso were reinforced, and the line underwent general maintenance, fully reopening on 30 January 2024.
Background
Metro system
The Sistema de Transporte Colectivo (STC) operates the Mexico City Metro,[3] one of the world's busiest urban transportation systems, which served approximately 4.5 million passengers daily in 2019, and the second-largest metro system in North America in 2021.[4][5][6]
Deterioration within the rail system resulted in multiple accidents and incidents, including a collision between two trains at Tacubaya metro station in March 2020, a railway coupler breaking while a train was operating near Misterios metro station the following month, a fire in the Metro's downtown headquarters in January 2021 that resulted in the death of a police officer, hospitalized thirty people, temporarily shut down six subway lines for several days, and a reported fire on metro tracks in April 2021.[7][6][8]
In December 2018, the recently appointed head of government of Mexico City, Claudia Sheinbaum, designated Florencia Serranía as the general director of the STC. Serranía had previously held the same position from 2004 to 2006 during the governorship of Andrés Manuel López Obrador,[9] who was president of Mexico at the time of the collapse.[10] From 2020 to April 2021, the position of STC deputy director-general of maintenance was vacant, and Serranía assumed management of that role.[11][12]
Line 12 and rolling stock

Line 12 operates from south-central Mexico City to the semi-rural southeastern borough of Tláhuac, serving approximately 350,000 passengers daily in 2019. In May 2021, it was the newest line in the Metro system.[7][8]
The head of government of Mexico City, Marcelo Ebrard, announced the line in August 2007, and construction commenced in September 2008.[13][14] Originally, the line was planned to be primarily underground, featuring 23 stations, 20 of which were to be underground (from Mixcoac to Nopalera), the section where the collapse occurred. The original budget for the project was MX$13 billion.[15]
The opening was initially expected to coincide with the 200th anniversary of Mexico's independence in 2010.[16] Multiple construction delays postponed its inauguration by Ebrard and required intervention from the federal government, led by the president Felipe Calderón.[17] The project was modified to have fewer underground stations and nine elevated stations (from Culhuacán to Zapotitlán).[16] Additionally, the elevated section would run along a different avenue than originally planned, Avenida Tláhuac .[18]
The line was constructed by Empresas ICA in association with Alstom Mexicana and Grupo Carso, the latter owned by business magnate Carlos Slim.[19] It was Carso's first project in railway construction, and they built the bridge between Calle 11 and Zapotitlán stations.[20][21] Ebrard and Calderón inaugurated the line in October 2012 a few months before the end of their terms.[7][22] The project's cost soared to MX$26 billion (US$1.29 billion as of 2021).[22][23]

The line runs FE-10 trains, a steel-wheeled model manufactured by Construcciones y Auxiliar de Ferrocarriles (CAF).[24] Francisco Bojórquez, the then-general director of the Metro system, advocated for rubber tires, considering them a safer option.[25] However, an internal labor commission disagreed, supporting the more cost-effective steel wheels.[26] Bojórquez explained that CAF trains have European specifications, but were promised to be ready one year before the proposed Bombardier trains, which followed American specifications.[19]
Line 12 was designed similarly to Line A, the other line in the system that uses steel-wheeled trains, with considerations based on the specifications of its Bombardier trains, which are 2.50 meters (8 ft 2 in) wide and weigh 170 metric tons (170 long tons; 190 short tons) per railcar. In contrast, the FE-10 trains are wider and heavier, measuring 2.80 meters (9 ft 2 in) in width and weighing 240 metric tons (240 long tons; 260 short tons) per railcar. The change was performed without considering the track requirements or reviewing the structural calculation of an elevated viaduct.[27][28]
Line 12 issues
Line 12 encountered issues with trains on elevated sections during its construction. Before pre-operational testing began, topographic monitoring detected subsidence on several columns.[28] Personnel recorded vibrations on the tracks in the Tláhuac area. Passenger testing commenced in June 2012; the Metro system noticed damage to approximately 10,000 ties due to vibrations in the following months.[28] Operations necessitated speeds as low as 5 km/h (3.1 mph) on some segments to prevent damage to the tracks. A congressional report indicated that coupling unprotected rails with substandard wheels could lead to train derailments,[7][22] and it received its safety certification one hour before its operation started.[19]
In March 2014, the city government closed the elevated section for twenty months for repairs due to technical and structural faults,[29] and established a special board to investigate the errors that led to it.[30] Thirty-three officials and former officials, including Enrique Horcasitas, the director of the Line 12 project, faced sanctions that included disqualifications from public work, fines, or both.[31]
The administration of Miguel Ángel Mancera, Ebrards's successor, hired SYSTRA in 2014 to conduct an independent investigation and provide a report. After reviewing over 2,900 documents and testing the tracks, the team concluded that errors occurred during the "planning, design, construction, and operation" of the line.[32][33] In a non-public report published by SinEmbargo.mx after the collapse, SYSTRA had noted that the wear and tear was unusual for a project that was only two years old, which they attributed to "mediocre quality" work. The group concluded that the Metro system would need to address the root causes of the wear to avoid future problems, as repairs would only serve as temporary fixes. They notified government authorities that a permanent resolution to the issues was infeasible and recommended developing a maintenance manual customized to the line's requirements for continuous operation.[34]
The Superior Auditor of the Federation (Auditoría Superior de la Federación; ASF) identified in 2015 twelve irregularities in the construction process, including the incompatibility between the train wheels and the rails, which could lead to track instability, while noting that train operations were within accepted safety limits.[35] According to Serranía, the French company Tricaud Société Organisée (TSO) was contracted in 2016 to maintain the daily operating conditions of the line's fixed installations and reported no concerns before the collapse.[36]
The 2017 Puebla earthquake damaged the line's tracks, leading to the temporary closure of six stations, from Tezonco metro station to the eastern terminal.[37][38] The Associated Press reported that experts advised closing the line for a comprehensive inspection instead of merely reinforcing it.[37] The ASF noted damage to the section that eventually collapsed.[39] Following the earthquake, residents reported visible structural cracks in the structure, prompting transport authorities to address these complaints.[4] In January 2018, they also repaired a column between Olivos and Nopalera stations that had cracks in its base.[40]
In 2019, residents provided photographs and videos to the authorities, expressing concerns that the bridge was buckling and that the structure was moving abnormally as trains passed.[41] By the end of that year, the engineering firm Ingeniería, Servicios y Sistemas Aplicados (ISSA) conducted a study on the structural and geotechnical behavior of the overpass, concluding that there was no risk to the line's operation.[36]
Collapse

On 3 May 2021 at 22:22 CDT (UTC−5), an eastbound train was traveling on the track between Olivos and Tezonco stations in Tláhuac.[42][43] Approximately 220 meters (720 ft) before reaching Olivos station,[44] the section of track between columns 12 and 13 collapsed due to a failure of the girder, causing the rear two train cars to derail.[45][10][46] The fallen railcars formed a V shape, with one car coming to rest on the ground and the other left suspended.[22][47] Debris from the collapse struck a vehicle traveling along Avenida Tláhuac, resulting in the death of the driver and injuries to his wife.[48] The overpass was approximately 5 meters (16 ft) above ground level, situated over a concrete median strip, which minimized casualties among motorists and pedestrians below.[49]
Twenty-six people died in the collapse, including fifteen reported deceased by midnight on 4 May, while ninety-eight others were hospitalized.[1][50] It marked the deadliest event for the Metro since 1975, when a collision between two trains resulted in the deaths of thirty-one passengers at Viaducto metro station.[51] It was the third fatal accident within fourteen months.[10] Following the collapse, twenty-two individuals were reported missing; by 6 May, the number was reduced to five.[52][53] According to the city government, it is likely that none of these individuals were on board the train, as they had been missing for several days prior to the accident.[54]
Rodrigo García, the driver of the train, felt a jolt just before arriving at Olivos station, after which his control panel indicated a power failure. García activated the emergency brake, exited the cab, and observed smoke and passengers evacuating from the last car. The control center instructed him to assess the situation and reassure the passengers accordingly. He was later informed of the collapse. In the fifth and last available car, García encountered injured and unconscious people, estimating that the train was three-quarters full.[55]
The STC warned residents to avoid the area.[3] Witnesses began rescue efforts, later joined by first-response teams.[56][57][58] Neighbors provided rescuers with coffee, water, and bread.[59][60] A nearby shopping mall cleared its parking lot to allow authorities to establish a control post.[61] Rescue operations were suspended after a few hours due to the structure instability.[62] A crane was deployed to lift sections of the train while search-and-rescue teams looked for survivors.[63] The first train car was removed the following day at 09:20 CDT, and the second car was removed before 14:00 on the same day.[61] All debris was cleared by the end of the month.[64][65]
Immediate aftermath

Service on Line 12 was suspended.[66][67] The following day, a rail replacement bus service was established, utilizing 490 city buses, which were inadequate to meet passenger demand. To enhance the service, the city contracted additional buses from Autobuses de Oriente, and added temporary bus routes to Tasqueña, Universidad, Atlalilco, and Coyuya metro stations.[68] The federal government declared three days of national mourning.[69] Social media users reported structural damage at other elevated stations, including Oceanía, Consulado, and Pantitlán; Sheinbaum stated that these stations would be inspected.[70] The general secretary of the Mexican Union of Metro Workers announced that approximately 8,000 workers would go on strike due to unsafe working conditions.[6][51]
Sheinbaum stated that the families of those who lost their lives would receive MX$700,000 (US$35,000) each,[71] which included MX$50,000 (US$2,500) from the city and MX$650,000 (US$32,650) from the Metro. This compensation was later increased to MX$1,870,000 per family.[72]
When Serranía was asked about satellite images showing that the collapsed section was slightly warped, she stated, "There is no such information; it is not true".[36] The National Regeneration Movement (MORENA), the ruling party in Mexico, voted against the establishment of a special commission to investigate the collapse, referring to the proposal as "vulturesque" and asserting that the collapse had no "urgent and obvious resolution".[73]
Reactions

Minutes after the collapse, Sheinbaum arrived at the accident site.[74] Ebrard, who was the Secretary of Foreign Affairs, said on Twitter, "What happened today in the Metro is a terrible tragedy ... My sympathy to the victims and their families".[75] The following morning, López Obrador extended his condolences and stated, "Nothing will be hidden; we should not fall into speculation ... no accusations will be made without evidence".[10][76] Carso announced that they would await official expert analyses before making any statements regarding the incident.[21][77]
Protests and tributes
In the days following the collapse, protesters expressed anger over the incident and the authorities' responses by vandalizing several Metro stations, breaking glass partitions and painting slogans such as "It wasn't an accident—It was negligence" on the walls.[51] Demonstrators marched from Periférico Oriente metro station to the accident site, carrying banners that read, "It was not an accident; those responsible have first and last names", and "Corruption kills, and the deaths are brought upon the people".[78] Local residents set up an altar in a shopping mall near the site of the collapse.[79] On 7 May, hundreds of protesters held a vigil at the scene, demanding justice.[80]
For Day of the Dead in 2021, local residents encouraged others to create a thematic altar called "Train to Mictlān".[81] On the eve of the first anniversary of the collapse, the National Action Party (PAN) installed a temporary sculpture on Paseo de la Reforma in front of the Antimonumento +43 memorial. It referenced the overpass collapse and featured the inscriptions "#FueMorena" (#ItWasMorena) and "La tragedia de la Línea 12" (The Tragedy of Line 12) on a wine-colored plinth, reflecting MORENA's colors.[82] On the anniversary of the collapse, family members, survivors, and residents visited the site to place altars and candles. They planned to establish a memorial at the site of the collapse.[83]
Investigations
The office of the federal Attorney General (FGR), along with its Mexico City counterpart (FGJCDMX) led by Ernestina Godoy Ramos, and the Norwegian risk management firm Det Norske Veritas (DNV) were appointed to investigate the collapse.[71][84]
DNV report
On 5 May 2022, the city government contracted DNV to conduct an investigation into the collapse.[85] The investigation was divided into three parts: the first part, costing MX$8,169,343, addressed the preliminary causes of the accident; the second part, which included the immediate cause, was set at MX$5,049,743; and the final part, costing MX$9,394,914, focused on the root cause and provided recommendations for the line's reopening.[86][87] According to the contract, DNV was authorized to "collect information for documentary analyses, covering design, construction, rehabilitation, intervention, operation, maintenance, and supervision" of the line up to the date of the collapse.[88]
DNV published the first part of the report on 16 June 2021, which identified structural faults associated with six construction deficiencies:[89]
- Poor welding process of Nelson studs
- Porosity and lack of fusion in the stud–beam joint
- Insufficient Nelson studs in the beams spanning the bridge assembly
- Use of different types of concrete in the girder
- Unfinished or improperly executed welds
- Inadequate supervision and dimensional control in fillet welds
DNV investigated the adequacy of the design and materials, assessed whether the structure's performance met the design requirements, and evaluated how operations, repairs, and renovations had affected the bridge.[89] The group reported that fewer bolts than necessary to support the structure had been installed and that the concrete covering them might have been faulty.[90] It found an alert issued by supervisors in August 2010 regarding the construction of the Tezonco–Olivos overpass, which said that only ten reinforcement bars were to be used in the bridge, despite the original project plans specifying twenty.[91] According to El Financiero, the final report omitted four additional lines of inquiry that were previously included in a draft report: "lateral-torsional buckling of the steel beams", "crushing of the concrete slab", "influence of loads from the railroad system", and "lack of infrastructure maintenance".[92]
DNV was initially expected to deliver the second part of the report on 14 July 2021; however, the group postponed it until 7 September of that year.[86][93] In the 180-page investigation, DNV concluded that the collapse was caused by a lack of functional Nelson studs in the affected section, which resulted in the buckling of the north and south beams. Insufficient functioning studs caused the girders to function independently in conditions for which they were not designed, leading to distortion in the central transverse frame and fatigue in the support. Additionally, poor distribution of the existing bolts and inadequate welds in the area contributed to the collapse.[94][95]
The third part of the report was initially expected in August 2021 but was delivered on 28 February of the following year.[86][96] The city government rejected the report's conclusions and withheld its publication. On 4 May 2022, Sheinbaum described the report as a "deficient, poorly produced, ... tendentious and false" document that presented "technical issues". She said that it served the interests of opposition parties, that DNV had unilaterally altered the methodology originally presented when the firm was hired, and that the company had a conflict of interest because one of DNV's lawyers had previously litigated against López Obrador. She announced a civil lawsuit against DNV and indicated that the firm would not receive payment for the final part of the report.[97][98][99] Andrés Lajous, the city's Secretary of Mobility, explained that the change in the report's methodology pertained to DNV's decision to "plant maintenance" as a cause of the collapse.[100] DNV maintained that their report was delivered "in accordance with the agreed [root cause analysis] methodology and to strict internal quality and revision procedures". The firm added that Héctor Salomón Galindo Alvarado, the referred lawyer, was hired in July 2019 and had no authority over the reports or investigations conducted by the company or being contracted by DNV México.[101][102]
On 9 May 2022, the Spanish newspaper El País published part of the third report, in which DNV concluded that the root cause of the accident was the bridge's design not complying with construction standards. Key factors included the lack of certification by an independent entity, inadequate supervision, changes to the original design, misplaced, poorly welded, or missing studs throughout the girders, and a lack of maintenance inspections from 2012 to 2019, despite recommendations for annual inspections in the ICA–Carso–Alstom manual.[103][104] The city government released the report two days later and explained the discrepancies they identified during a conference. Officials expressed their opposition to the report because:[105]
- DNV did not compare the collapsed section with similar segments
- DNV relied on Google tools, including Google Street View, despite a disclaimer indicating that the data may not reflect actual conditions
- DNV initially claimed that the deformations were not visible to the naked eye but later contradicted this using Google Street View images
- The ICA–Carso–Alstom maintenance manual did not specify methodologies for assessing deformation criteria
- The report initially stated that no maintenance reports were provided but later acknowledged that reports for 2019 and 2020 did exist
- DNV did not follow the requested methodology.
Sheinbaum announced that the contract with DNV would be terminated and that a group of engineers would be hired to "present the complete truth".[106]
Other investigations
Three days before DNV released its report, journalists from The New York Times (NYT) published an investigation attributing the collapse to a series of errors originating in its planning. The report indicated that the line was built hastily as Ebrard's administration was nearing its end, and steel studs connecting the steel to the concrete slab failed due to poor-quality welds and failure to remove ceramic rings. It also noted that the city approved substandard work and that audits after the 2017 earthquake revealed errors in the original construction, including missing steel components and improperly poured concrete.[19] Sheinbaum criticized the NYT article, asserting that the newspaper has sought to confront the Fourth Transformation—the president's political platform.[108] Ebrard stated that the collapse resulted from a lack of maintenance rather than structural faults.[109]
The FGJCDMX investigation found results similar to DNV's initial report. It revealed that shear bolts connecting the concrete slabs to the beams were misaligned, and in some cases, the studs were not fused with the beams, causing distortion-related fatigue. The report concluded that the collapse occurred when the eastbound beam suddenly failed, dragging the westbound beam down within 1.9 seconds.[110][111] Additionally, a study by specialists for the FGR indicated that the collapsed section had only 65 percent of the necessary bolts.[112] They noted a lack of inspection reports addressing bridge issues, stating that existing deformities and defects could have been identified with proper maintenance and specialized examinations.[113]
The College of Civil Engineers of Mexico (Colegio de Ingenieros Civiles de México; CICM) conducted independent studies of Line 12, excluding the collapsed area. They found that the bridge features two types of girders: concrete girders built by ICA from Culhuacán to Calle 11 stations, and steel girders built by Carso from Calle 11 to Zapotitlán stations.[107][21] The study found that 68 percent of the elevated section exhibited minor and common deficiencies, while the remaining 32 percent—between Periférico Oriente and Zapotitlán stations—showed vulnerabilities requiring further analysis. These vulnerabilities included poor welds, improper spacing between beams, cracks in columns and beams, and irregularities in the steel structure support.[107][114] The institution recommended a reinforcement and rehabilitation project before any reopening,[115] and cautioned against reopening the underground section, as the railway workshops necessary for train maintenance are situated after Tláhuac metro station, the line's terminus.[116]
Reconstruction and reopening
Sheinbaum stated that the reconstruction of the collapsed section was anticipated to be finished by the end of 2022.[117] A week after the collapse, STC considered reopening only the underground segment.[118]
In June 2021, Sheinbaum discussed with ICA and Carso their potential financial responsibility for the reconstruction of the elevated section.[119] On 22 June, López Obrador met with Sheinbaum and Slim, where they reached an agreement that Slim would assist with the reconstruction. López Obrador emphasized the urgency, stating that the work should be completed "as soon as possible" and aimed for Line 12 to be operational "within a year at the latest, with full safety".[120][121] A week later, López Obrador announced that Carso had agreed to rebuild the collapsed section at no cost,[122][123] and Slim remarked:
I am convinced that [the line] was built by the best engineers in Mexico, who did the calculations and the design, and if you remember, in October 2012, around November ... the project was approved, which had been done by international experts. I am convinced that from its origin, it has no flaws. So much so that the president of the Republic, the head of government, and the elected head of government rode on it, and many of us were invited to tour it, covering about 12 kilometers (7.5 mi).[a]

Reconstruction of the collapsed section began on 16 February 2022.[125] A total of 6.7 km (4.2 mi) underwent strengthening with column reinforcements and supports, including struts, diaphragms, and tensors.[126] A girder located 200 metres (660 ft) from the accident site was dismantled and rebuilt. According to the Guacamaya Leaks, which involved multiple internet leaks of classified documents from the Secretariat of National Defense by the hacktivist group Guacamaya, Mexico City authorities requested the army to donate 20,000 t (20,000 long tons; 22,000 short tons) of steel for the girders' reinforcement. This steel was originally intended for the canceled Texcoco Airport, and the army provided 13,000 t (13,000 long tons; 14,000 short tons).[127] Sheinbaum confirmed this information, stating that the unused material from the construction of Felipe Ángeles International Airport was repurposed for the reinforcement of Line 12.[128]
The subway section of Line 12, which runs from Mixcoac to Atlalilco stations, reopened on 15 January 2023.[129] In preparation for the section reopening, 15,000 ties and rails were replaced in interstation tunnels, leaks were repaired, and the track ballast was upgraded to a firmer material. The section operated thirteen trains and was patrolled by members of the National Guard, who were deployed to all metro stations following the 2023 Mexico City Metro train crash, amid Sheinbaum's allegations that the system was under attack from saboteurs.[130][131] The next section, from Culhuacán to Periférico Oriente stations, opened on 15 July 2023.[132] The last section, including the area where the collapse occurred, reopened on 30 January 2024.[133]
Aftermath and litigation
After the first DNV report, Grupo Carso lost MX$7.8 billion on the Mexican Stock Exchange.[134] They lost an additional MX$2.7 billion after announcing plans to rebuild the collapsed section.[135] Just days before the second report's delivery, DNV filed a complaint with the FGJCDMX due to a breach in the chain of custody regarding a package sent to the United States for further studies. Upon its return to Mexico, the box containing the samples had been tampered with, which could impact the investigation.[136]
In August 2021, the FGJCDMX initiated an investigation into eleven welders and two supervisors.[137] By October, charges of manslaughter, injury, and property damage were announced against Horcasitas, along with nine former officials and supervisors. Many of these individuals had been disqualified from public office in 2014 and 2015 for their roles in the project's planning and construction.[138][139] Horcasitas' defense argued that errors arose when the city sought to modify the original project and contracted different companies, claiming that the line's infrastructure had not received proper maintenance since its opening.[140] The defense also pointed out that the Spanish version of DNV's report omitted maintenance-related information.[141] The ten former officials were charged in December 2021 and are awaiting trial As of January 2023.[142]
Carso estimated that the reconstruction and reinforcement of the collapsed bridge would cost MX$800 million.[143] In November 2021, the company stated that it had subcontracted the stud-welding company J. J. Jiménez, S. A. de C. V. in 2010, and that Carso had supervised the work through a verification system that assessed the welding of the studs, their alignment, and their final positions.[144]
By February 2022, 80 percent of those affected had received compensation from Carso as part of a deal stipulating that they would not pursue legal action or seek additional payments.[145] This percentage increased to 90 percent by May 2022.[146] Compensation amounts varied based on the severity of injuries, ranging from 450,000 to six million pesos (about US$21,600 to 290,000) for the families of deceased victims. Carso retained the right to seek reimbursement from those found legally responsible for the collapse and to take legal action against them.[145][147][148] By February 2022, the remaining parties who had not accepted the compensation were pursuing legal action against Carso.[149]
Sheinbaum and Ebrard were both candidates for MORENA in the 2024 presidential election.[150] According to international journalists, the collapse could have impacted their presidential campaigns, as Ebrard oversaw the construction of Line 12, regarded as his signature infrastructure project, while Sheinbaum had over two years to address concerns about the line's condition and ensure its proper maintenance.[6][23][150]
Notes
- ^ Original text in Spanish: "... estoy convencido de que la hicieron los mejores calculistas de México, hicieron los cálculos, el diseño y si recordarán en octubre de 2012, por ahí de noviembre [...], se dio el visto bueno al proyecto, lo que se había hecho por expertos internacionales, lo cual estoy convencido que desde su origen no tiene vicios. Tan es así que se subió el presidente de la República, el jefe de Gobierno y el jefe de Gobierno electo y nos invitaron a muchas gentes a recorrer, recorrimos como 12 kilómetros".[124]
References
- ^ a b c Piña, Jessica (2 May 2022). "A un año del accidente de la Línea 12 del metro" [One Year After the Line 12 Metro Accident]. MVS Noticias. Archived from the original on 2 May 2022. Retrieved 7 May 2022.
- ^ Olvera, Dulce (4 May 2021). "El conductor del tren de la L12 está hospitalizado. Trabajadores exigen revisar todo el Metro" [The driver of the L12 train is hospitalized. Workers demand to overhaul the entire Metro]. SinEmbargo.mx (in Spanish). Archived from the original on 5 May 2021. Retrieved 5 May 2021.
- ^ a b "What We Know About the Mexico City Train Crash". The New York Times. 4 May 2021. ISSN 0362-4331. Archived from the original on 4 May 2021. Retrieved 4 May 2021.
- ^ a b "Mexico City metro overpass collapse kills 23". BBC News. 4 May 2021. Archived from the original on 4 May 2021. Retrieved 4 May 2021.
- ^ "Afluencia de estación por línea 2019" [Station traffic by line in 2019] (in Spanish). Sistema de Transporte Colectivo Metro. 2020. Archived from the original on 8 April 2020. Retrieved 4 May 2021.
- ^ a b c d Sheridan, Mary Beth (4 May 2021). "Mexico City subway overpass collapses; at least 13 dead as metro cars topple". The Washington Post. Archived from the original on 4 May 2021. Retrieved 4 May 2021.
- ^ a b c d Lopez, Oscar; Ives, Mike; Taylor, Derrick Bryson (4 May 2021). "Mexico City's metro has been plagued by problems". The New York Times. Archived from the original on 4 May 2021. Retrieved 4 May 2021.
- ^ a b Agren, David (4 May 2021). "Anger mounts as death toll from Mexico metro overpass collapse rises to 24". The Guardian. Archived from the original on 4 May 2021. Retrieved 4 May 2021.
- ^ Camhaji, Elías (28 June 2021). "Sheinbaum deja caer a la jefa del metro de Ciudad de México casi dos meses después del colapso de la Línea 12" [Sheinbaum lets go of the head of the Mexico City Metro nearly two months after the collapse of Line 12]. El País (in Spanish). Archived from the original on 8 October 2021. Retrieved 15 February 2025.
- ^ a b c d McDonnell, Patrick J.; Sánchez, Cecilia (9 May 2021). "Her 12-year-old son took Metro to buy her a Mother's Day present. He never returned". Los Angeles Times. Archived from the original on 9 May 2021. Retrieved 10 May 2021.
- ^ Navarrete, Shelma (4 May 2021). "STC Metro mantuvo vacante un año la subdirección de Mantenimiento" [STC Metro kept the deputy maintenance director position vacant for a year]. Expansión (in Spanish). Archived from the original on 24 June 2021. Retrieved 23 June 2021.
- ^ Escalona, Hilda (30 April 2021). "Un año después, el Metro ya tiene encargado de mantenimiento" [A year later, the Metro now has a maintenance manager]. El Sol de México (in Spanish). Archived from the original on 24 June 2021. Retrieved 23 June 2021.
- ^ Bolaños, Ángel; Quintero, Josefina (9 August 2007). "Presentó Ebrard el proyecto de la línea 12 del Metro, que irá de Tláhuac a Mixcoac" [Ebrard presented the project for Line 12 of the Metro, which will run from Tláhuac to Mixcoac]. La Jornada (in Spanish). Archived from the original on 26 February 2021. Retrieved 20 June 2021.
- ^ Castillejos, Jessica (21 September 2008). "Línea 12 arranca construcción a vapor" [Construction of Line 12 begins in full swing]. Excélsior (in Spanish). Archived from the original on 9 December 2008. Retrieved 4 May 2021.
- ^ Rosas, Obed (18 June 2021). "L12 va a su tercer remiendo en 7 años en zona que no debió existir" [Line 12 is undergoing its third repair in 7 years in an area that should not have existed]. SinEmbargo.mx (in Spanish). Archived from the original on 18 June 2021. Retrieved 18 June 2021.
- ^ a b Zamarrón, Israel (6 May 2021). "Línea 12 debió ser subterránea, pero por ahorrar dinero, se hizo tramo elevado" [Line 12 was supposed to be underground, but to save money, an elevated section was constructed]. Forbes México (in Spanish). Archived from the original on 18 June 2021. Retrieved 18 June 2021.
- ^ Cabrera, Rafael (5 May 2021). "Expresidente mexicano no intervino en diseño de línea de Metro accidentada" [The former Mexican president did not intervene in the design of the accidented Metro line]. Associated Press News. Archived from the original on 24 August 2022. Retrieved 15 February 2025.
- ^ Ramírez, Claudia (4 May 2021). "La línea 12 del Metro: crónica de una tragedia anunciada" [Line 12 of the Metro: a chronicle of a forewarned tragedy]. Infobae (in Spanish). Archived from the original on 7 October 2024. Retrieved 6 October 2024.
- ^ a b c d Kitroeff, Natalie; Abi-Habib, Maria; Glanz, James; Lopez, Oscar; Cai, Wiyi; Grothjan, Evan; Peyton, Miles; Cegarra, Alejandro (13 June 2021). "Why the Mexico City Metro Collapsed". The New York Times. Archived from the original on 20 June 2021. Retrieved 20 June 2021.
- ^ Abi-Habib, Maria; Lopez, Oscar; Kitroeff, Natalie (16 June 2021). "Construction Flaws Led to Mexico City Metro Collapse, Independent Inquiry Shows". The New York Times. Archived from the original on 7 October 2024. Retrieved 7 October 2024.
- ^ a b c "Esperaremos a los peritajes oficiales: Carso" [We Will Await the Official Expert Reports: Carso]. Aristegui Noticias (in Spanish). 4 May 2021. Archived from the original on 4 May 2021. Retrieved 5 May 2021.
- ^ a b c d Stevenson, Mark (5 May 2021). "Mexico City subway collapse was a tragedy foretold". Associated Press. Archived from the original on 5 May 2021. Retrieved 6 May 2021.
- ^ a b "Mexico City 'Golden Line' under suspicion after crash". France 24. 4 May 2021. Archived from the original on 6 May 2021. Retrieved 6 May 2021.
- ^ Carrillo, Emmanuel (6 May 2021). "El otro 'dolor de cabeza': los trenes y la vía de la L12" [The other 'headache': the trains and track of Line 12]. Forbes. Archived from the original on 18 April 2024. Retrieved 15 February 2025.
- ^ Cedillo, Óscar (21 June 2021). "Línea 12 del Metro: todos fallaron" [Line 12: Everyone failed]. Milenio (in Spanish). Mexico City. Retrieved 15 February 2025.
- ^ "Una elección contradictoria; Trenes de la Línea 12" [A contradictory election; Line 12 trains]. Excélsior. Mexico City. 7 July 2014. Archived from the original on 20 May 2021. Retrieved 7 September 2021.
- ^ "Línea 12: rentó Ebrard trenes más anchos, sin licitar, y reservó datos" [Line 12: Ebrard rented wider trains without a bidding process and withheld information]. La Razón (in Spanish). 13 March 2014. Archived from the original on 5 May 2021. Retrieved 25 September 2021.
- ^ a b c Celis, Darío (7 May 2021). "El desastre de la Línea 12" [The disaster of Line 12]. El Financiero (in Spanish). Archived from the original on 18 May 2021. Retrieved 25 September 2021.
- ^ Romo, Mario (10 May 2021). "The deadly collapse of Mexico City's 'Golden Line' was a tragedy foretold". CNN. Archived from the original on 4 December 2024. Retrieved 15 February 2025.
- ^ Ruiz, Kevin (30 January 2024). "Línea 12 del Metro: Cronología del colapso en el tramo elevado de Olivos a Tezonco" [Line 12 of the Metro: Chronology of the Collapse on the Elevated Section from Olivos to Tezonco]. El Universal. Archived from the original on 10 May 2024. Retrieved 15 February 2025.
- ^ Romero Puga, Juan Carlos (5 May 2021). "Fantasmas de la línea 12" [Ghosts of Line 12]. Letras Libres (in Spanish). Archived from the original on 9 November 2024. Retrieved 15 February 2025.
- ^ "Línea 12 del Metro falló en diseño y construcción" [Line 12 of the Metro failed in design and construction]. Forbes México (in Spanish). 5 September 2014. Archived from the original on 4 May 2021. Retrieved 4 May 2021.
- ^ "Cronología y fechas clave en la Línea 12 del Metro" [Chronology and key dates on Metro Line 12]. El Universal (in Spanish). Mexico City. 4 May 2021. Archived from the original on 4 May 2021. Retrieved 4 May 2021.
- ^ Barragán, Daniela (17 May 2021). "Informe de 2014, oculto por años, revelaba ya el desastre de la L12" [A 2014 report, hidden for years, already revealed the disaster of Line 12]. SinEmbargo.mx. Archived from the original on 17 May 2021. Retrieved 25 December 2021.
- ^ González, Isabella (4 May 2021). "Las irregularidades de la Línea 12" [The irregularities of Line 12]. LatinUS. Archived from the original on 5 May 2021. Retrieved 4 May 2021.
- ^ a b c Hernández, Eduardo (4 May 2021). "Florencia Serranía asegura que no tenían reportes de afectaciones en la Línea 12" [Florencia Serranía stated that there were no reports of issues on Line 12]. El Universal. Mexico City. Archived from the original on 5 May 2021. Retrieved 5 May 2021.
- ^ a b Castillo, E. Eduardo; Verza, Maria (6 May 2021). "Survivor of Mexico City subway collapse reflects on the decision to change cars". WTVD. AP. Archived from the original on 7 May 2021. Retrieved 9 May 2021.
- ^ Hernández, Eduardo (21 September 2017). "Vecinos temen colapso de Línea 12 del Metro por sismo" [Residents fear the collapse of Line 12 of the Metro due to the earthquake]. El Universal (in Spanish). Mexico City. Archived from the original on 4 May 2021. Retrieved 4 May 2021.
- ^ "Reportaron errores y daños antes y después del sismo de la Línea 12 del Metro" [Errors and damage were reported before and after the earthquake on Line 12 of the Metro] (in Spanish). Mexico City: Canal 44. Archived from the original on 6 May 2021. Retrieved 22 June 2021.
- ^ "Vecinos de la Línea 12 alertaron por grietas... en 2017" [Residents of Line 12 raised alarms about cracks... in 2017]. Chilango (in Spanish). 4 May 2021. Archived from the original on 4 May 2021. Retrieved 4 May 2021.
- ^ Fuentes, David (4 May 2021). "Otra vez brota la solidaridad de extraños por accidente en Línea 12 del Metro" [Once again, solidarity among strangers emerges following the accident on Line 12 of the Metro]. El Universal. Archived from the original on 4 May 2021. Retrieved 4 May 2021.
- ^ Pantoja, Sara (2 May 2022). "Víctimas denuncian abandono del gobierno de Sheinbaum a un año del colapso en la Línea 12" [Victims Denounce Government Abandonment by Sheinbaum One Year After the Line 12 Collapse]. Proceso (in Spanish). Archived from the original on 5 May 2022. Retrieved 5 May 2022.
- ^ "Accidente Metro CDMX Línea 12: Resumen de noticias, número de víctimas y daños por colapso en estación Olivos" [Mexico City Metro Line 12 Accident: Summary of News, Number of Victims, and Damage from Collapse at Olivos Station]. Marca (in Spanish). 5 May 2021. Archived from the original on 24 June 2021. Retrieved 23 June 2021.
- ^ "Qué provocó la tragedia en la Línea 12: estas serían las causas del desplome de un tramo del Metro de la CDMX" [What Caused the Tragedy on Line 12: These Would Be the Causes of the Collapse of a Segment of the Mexico City Metro]. Infobae (in Spanish). 4 May 2021. Archived from the original on 5 May 2021. Retrieved 4 May 2021.
- ^ Estrada G., María de los Ángeles; Granados Gómez, Juan Pablo (18 June 2021). "#ColumnaInvitada – La tragedia de la Línea 12 del Metro sigue sin responsables" [#GuestColumn – The Tragedy of Line 12 of the Metro Remains Without Accountability]. Expansión (in Spanish). Archived from the original on 18 June 2021. Retrieved 19 June 2021.
- ^ "Puente del Metro cae en estaciones Olivos y Tezonco de la Línea 12" [Metro Bridge Collapses at Olivos and Tezonco Stations on Line 12]. Milenio (in Spanish). 3 May 2021. Archived from the original on 4 May 2021. Retrieved 4 May 2021.
- ^ Diaz, Jaclyn; Neumann, Scott (4 May 2021). "Mexico City Metro Train Derails, Killing At Least 23 And Injuring Dozens". NPR. Archived from the original on 6 May 2021. Retrieved 6 May 2021.
- ^ Nila, Gabriela (4 May 2021). "Confirman muerte de conductor de coche aplastado por desplome de metro Olivos; viajaba con su esposa" [Driver Killed by Metro Collapse at Olivos Station Confirmed; He Was Traveling with His Wife]. Noticieros Televisa (in Spanish). Archived from the original on 5 May 2021. Retrieved 4 May 2021.
- ^ Sánchez, Fabiola (4 May 2021). "Overpass collapse on Mexico City metro kills at least 24". Associated Press News. Archived from the original on 4 May 2021. Retrieved 4 May 2021.
- ^ Andrew Herrera, Karina (4 May 2021). "Suman 15 muertos y 34 hospitalizados por desplome de trabe en Línea 12: Sheinbaum" [15 Dead and 34 Hospitalized Due to Beam Collapse on Line 12: Sheinbaum]. Noticieros Televisa (in Spanish). Archived from the original on 4 May 2021. Retrieved 19 October 2021.
- ^ a b c McDonnell, Patrick J.; Linthicum, Kate; Sánchez, Cecilia (4 May 2021). "In Mexico, a deadly train wreck that many saw coming". Los Angeles Times. Mexico City. Archived from the original on 4 May 2021. Retrieved 5 May 2021.
- ^ "Identifican a Brandon, de 12 años entre fallecidos por colapso en el Metro; 22 personas siguen desaparecidas" [Brandon, 12, Identified Among the Deceased from Metro Collapse; 22 People Remain Missing]. Animal Político (in Spanish). 4 May 2021. Archived from the original on 5 May 2021. Retrieved 6 May 2021.
- ^ "Línea 12 del Metro: Aún hay 5 personas desaparecidas" [Line 12 of the Metro: 5 People Still Missing]. La Razón. 6 May 2021. Archived from the original on 7 May 2021. Retrieved 8 May 2021.
- ^ Pantoja, Sara (6 May 2021). "CDMX asegura que cinco personas desaparecidas no tienen relación con colapso en L-12" [Mexico City Asserts That Five Missing Persons Are Not Linked to Line 12 Collapse]. Proceso (in Spanish). Mexico City. Archived from the original on 24 June 2021. Retrieved 19 June 2021.
- ^ Camhaji, Elías (7 May 2021). "El conductor de metro que sobrevivió a la tragedia de la Línea 12: 'Nunca esperas que te pase algo así'" [The Metro Driver Who Survived the Line 12 Tragedy: 'You Never Expect Something Like This to Happen to You']. El País (in Spanish). Archived from the original on 15 June 2021. Retrieved 19 October 2021.
- ^ "Puente se desploma con todo y tren del Metro en estación Olivos de la L12, en la CDMX" [Bridge Collapses with Train at Olivos Station on Line 12 in Mexico City]. Diario de Colima (in Spanish). 3 May 2021. Archived from the original on 4 May 2021. Retrieved 4 May 2021.
- ^ "Survivors Helped From Wreckage After Deadly Mexico City Overpass Collapse". Yahoo!. 4 May 2021. Archived from the original on 5 May 2021. Retrieved 4 May 2021.
- ^ Patiño, Daniela (4 May 2021). "Hay gente aplastada bajo las estructuras del Metro. Sacarlas va a tardar, dice miembro de los Topos en México" [There are people trapped under the Metro structures. It will take time to rescue them, says a member of the Topos in Mexico]. CNN en Español (in Spanish). Archived from the original on 24 June 2021. Retrieved 24 June 2021.
- ^ Rodríguez, Juan Carlos (4 May 2021). "Todos parecían estar muertos" [Everyone appeared to be dead]. Eje Central (in Spanish). Archived from the original on 5 May 2021. Retrieved 5 May 2021.
- ^ "¡Solidaridad presente! Así se unieron las personas tras colapso de la Línea 12 del Metro" [Solidarity in Action! Here's How People Came Together After the Line 12 Metro Collapse]. Publimetro (in Spanish). 4 May 2021. Archived from the original on 5 May 2021. Retrieved 5 May 2021.
- ^ a b Rodríguez, Darinka; Vaerla, Micaela; Arroyo, Lorena (4 May 2021). "'Resistan tantito': la solidaridad de los vecinos de Tláhuac minutos después del derrumbe del metro" ['Hang in There a Little Longer': The Solidarity of Tláhuac Neighbors Minutes After the Metro Collapse]. El País (in Spanish). Mexico. Archived from the original on 5 May 2021. Retrieved 5 May 2021.
- ^ "Claudia Sheinbaum informa suspensión en maniobras de rescate; 'estructura está muy débil'" [Claudia Sheinbaum Reports Suspension of Rescue Operations; 'The Structure Is Very Weak']. El Heraldo de México (in Spanish). 4 May 2021. Archived from the original on 4 May 2021. Retrieved 4 May 2021.
- ^ "Mexico City rail overpass collapses, killing 20 people". Reuters. 4 May 2021. Archived from the original on 4 May 2021. Retrieved 4 May 2021.
- ^ "Concluyen retiro de estructura tras tragedia en Metro de CDMX" [Removal of Structure Completed After Tragedy at Mexico City Metro]. El Informador (in Spanish). 31 May 2021. Archived from the original on 24 June 2021. Retrieved 23 June 2021.
- ^ "Remoción en Línea 12 de Metro CDMX deja 3 trabajadores heridos" [Removal on Line 12 of Mexico City Metro leaves three workers injured]. Azteca Noticias (in Spanish). TV Azteca. 28 May 2021. Archived from the original on 24 June 2021. Retrieved 23 June 2021.
- ^ "Mexico City metro overpass collapse kills 23". BBC News. 4 May 2021. Archived from the original on 4 May 2021. Retrieved 4 May 2021.
- ^ "Cierran toda la Línea 12 del Metro; RTP brindará servicio de apoyo" [Entire Line 12 of the Metro Closed; RTP to Provide Support Service]. Chilango (in Spanish). 4 May 2021. Archived from the original on 4 May 2021. Retrieved 4 May 2021.
- ^ As mentioned by the following sources:
- "CdMx suma camiones ADO a transporte emergente por accidente en L12 del Metro" [Mexico City Adds ADO Buses to Emergency Transportation Following Line 12 Metro Accident]. Milenio (in Spanish). Mexico City. 5 May 2021. Archived from the original on 5 May 2021. Retrieved 5 May 2021.
- Delgado, Karen (2 May 2022). "Horas en el transporte y tráfico: así cambió la vida el cierre de la Línea 12" [Hours spent on transportation and traffic: This is how the closure of Line 12 changed daily life]. Chilango. Retrieved 15 February 2025.
- Morales, Amallely (26 May 2021). "Corre Metrobús emergente en Tláhuac" [Emergency Metrobús Service in Tláhuac]. Reforma (in Spanish). Archived from the original on 10 September 2021. Retrieved 26 May 2021.
- "Anuncian nueva ruta de Metrobús para la Línea 12 de Tláhuac a Coyuya" [New Metrobús Route Announced from Tláhuac to Coyuya for Line 12] (in Spanish). ADN 40. 18 June 2021. Archived from the original on 24 June 2021. Retrieved 19 June 2021.
- ^ "AMLO decreta tres días de luto nacional por accidente en Línea 12 del Metro" [AMLO Declares Three Days of National Mourning for Line 12 Metro Accident]. El Universal (in Spanish). 5 May 2021. Archived from the original on 5 May 2021. Retrieved 5 May 2021.
- ^ Hernández, Eduardo (4 May 2021). "Se revisarán denuncias por cuarteaduras en Metro Oceanía y Pantitlán: Sheinbaum" [Sheinbaum: Reports of Cracks in Oceanía and Pantitlán Metro Stations Will Be Investigated]. El Universal (in Spanish). Archived from the original on 5 May 2021. Retrieved 5 May 2021.
- ^ a b "Mexico City metro collapse victims' families to get compensation". Al Jazeera. 8 May 2021. Archived from the original on 10 May 2021. Retrieved 10 May 2021.
- ^ Vargas Isita, Héctor (3 September 2021). "Dan más de 48 millones de pesos a familias de víctimas del desplome de L12 del Metro" [Over 48 Million Pesos Granted to Families of Victims of Line 12 Metro Collapse]. Noticieros Televisa (in Spanish). Archived from the original on 7 September 2021. Retrieved 8 September 2021.
- ^ Gamboa, Víctor (6 May 2021). "Morena frena creación de una Comisión Investigadora del colapso de Metro Olivos" [MORENA Halts the Creation of an Investigative Commission for the Olivos Metro Station Collapse]. El Universal (in Spanish). Archived from the original on 8 May 2021. Retrieved 8 May 2021.
- ^ "Claudia Sheinbaum se traslada al lugar del accidente, en la Línea 12 del Metro" [Claudia Sheinbaum Travels to the Accident Site on Line 12 of the Metro]. Milenio (in Spanish). Mexico City. 3 May 2021. Archived from the original on 4 May 2021. Retrieved 5 May 2021.
- ^ Castillo, Eduardo; Verza, María (4 May 2021). "'Lo ocurrido hoy en el Metro es una terrible tragedia'" ['What happened today in the Metro is a terrible tragedy']. Chicago Tribune (in Spanish). Archived from the original on 5 May 2021. Retrieved 5 May 2021.
- ^ Lozano, Nayelo (4 May 2021). "AMLO respalda a Sheinbaum tras colapso en L12: no se ocultará nada, no se acusará sin pruebas" [AMLO Supports Sheinbaum After Line 12 Collapse: 'Nothing Will Be Hidden, No Accusations Without Evidence']. Político.mx. Archived from the original on 4 May 2021. Retrieved 5 May 2021.
- ^ Sánchez, Axel (4 May 2021). "Grupo Carso esperará los peritajes tras colapso en Línea 12 del Metro" [Grupo Carso Will Await Official Expert Reports After Line 12 Metro Collapse]. El Financiero (in Spanish). Archived from the original on 4 May 2021. Retrieved 5 May 2021.
- ^ Quintero M., Josefina (4 May 2021). "Con marcha exigen castigo a responsables de accidente en L12" [With a March, Protestors Demand Accountability for Those Responsible for the Line 12 Accident]. La Jornada (in Spanish). Mexico City. Archived from the original on 5 May 2021. Retrieved 4 May 2021.
- ^ Espino, Manuel; Ruiz, Kevin (4 May 2021). "Colocan altar en memoria de las personas fallecidas en accidente de Línea 12 del Metro" [An Altar Is Set Up in Memory of Those Who Died in the Line 12 Metro Accident]. El Universal (in Spanish). Archived from the original on 8 May 2021. Retrieved 8 May 2021.
- ^ "Mexico City metro: Hundreds protest at scene of deadly rail collapse". BBC News. 9 May 2021. Archived from the original on 9 May 2021. Retrieved 10 May 2021.
- ^ Osorio, Karen (28 October 2021). "Tren al Mictlán: convocan a ofrenda de Día de Muertos para víctimas en colapso de L12" [Train to Mictlán: Call for Day of the Dead Offering for Victims of Line 12 Collapse]. Debate (in Spanish). Archived from the original on 4 November 2021. Retrieved 2 May 2022.
- ^ "#FueMorena: PAN CDMX coloca antimonumento por víctimas de la Línea 12 del Metro" [#FueMorena: PAN Mexico City Installs Anti-Monument for Victims of the Line 12 Metro] (in Spanish). 2 May 2022. Archived from the original on 3 May 2022. Retrieved 2 May 2022.
- ^ Guzmán, Sharenii (3 May 2022). "A un año de la caída de la Línea 12, sobrevivientes y familiares de personas fallecidas anuncian un memorial" [One Year After the Collapse of Line 12, Survivors and Families of the Deceased Announce a Memorial]. Animal Político (in Spanish). Archived from the original on 4 May 2022. Retrieved 5 May 2022.
- ^ Parsons, Jim (9 May 2021). "Forensics Firm DNV Tapped to Probe Mexico City Subway Collapse". Engineering News-Record. Archived from the original on 10 May 2021. Retrieved 10 May 2021.
- ^ "El día que Claudia Sheinbaum expresó su confianza a DNV para 'llegar al fondo' del colapso de la Línea 12" [The Day Claudia Sheinbaum Expressed Her Confidence in DNV to 'Get to the Bottom' of the Line 12 Collapse]. Infobae (in Spanish). 5 May 2022. Archived from the original on 8 May 2022. Retrieved 11 May 2022.
- ^ a b c Cervantes, Mariana (17 June 2021). "¿Qué son la causa inmediata y la causa raíz, explicaciones del colapso en Línea 12 del Metro?" [What are the immediate cause and the root cause, explanations for the collapse of Line 12 of the Metro?]. Radio Fórmula (in Spanish). Archived from the original on 19 June 2021. Retrieved 20 June 2021.
- ^ "Pactaron tres pagos por informes de DNV" [Three Payments Agreed for DNV Reports]. MSN (in Spanish). El Universal. 5 May 2022. Archived from the original on 12 May 2022. Retrieved 11 May 2022.
- ^ Gómez Leyva, Ciro (6 May 2022). "Gobierno CDMX inicia demanda contra empresa noruega DNV" [Mexico City Government Initiates Lawsuit Against Norwegian Company DNV]. Imagen Televisión. Archived from the original on 12 May 2022. Retrieved 11 May 2022.
- ^ a b Vela, Daniel Saúl; Alzaga, Ignacio (16 June 2021). "Peritaje Línea 12: Estas son las 6 deficiencias en la construcción que se encontraron" [Line 12 Expert Report: These Are the 6 Construction Deficiencies Identified]. El Financiero (in Spanish). Archived from the original on 17 June 2021. Retrieved 20 June 2021.
- ^ Stevenson, Mark (16 June 2021). "Report blames poor welds for Mexico City subway collapse". Associated Press. Archived from the original on 24 June 2021. Retrieved 21 June 2021.
- ^ Vela, Daniel Saúl; Alzaga, Ignacio (18 June 2021). "Otra revelación del peritaje de la Línea 12: se buscó usar menos varilla" [Another Revelation from the Line 12 Expert Report: Efforts Were Made to Use Fewer Reinforcement Bars]. El Financiero (in Spanish). Archived from the original on 19 June 2021. Retrieved 20 June 2021.
- ^ Vela, Daniel Saúl; Alzaga, Ignacio (17 June 2021). "Peritaje Línea 12: suprimen de 'última hora' el tema del mantenimiento" [Line 12 Expert Report: Maintenance Issue Removed 'At the Last Minute']. El Financiero (in Spanish). Archived from the original on 17 June 2021. Retrieved 20 June 2021.
- ^ Ramos, Rolando (16 June 2021). "Informe preliminar de DNV revela deficiencias en la Línea Dorada" [Preliminary Report from DNV Reveals Deficiencies in the Golden Line]. El Economista (in Spanish). Archived from the original on 21 June 2021. Retrieved 20 June 2021.
- ^ "Missing bolts contributed to Mexico City metro collapse: Report". Al Jazeera English. 7 September 2021. Archived from the original on 8 September 2021. Retrieved 8 September 2021.
- ^ "Report blames poor welds for Mexico City subway collapse". ABC News. Associated Press. 7 September 2021. Archived from the original on 7 September 2021. Retrieved 8 September 2021.
- ^ Rodríguez, Iván (5 May 2022). "Gobierno de CDMX rescinde contrato y demanda a DNV" [Government of Mexico City Terminates Contract and Sues DNV]. El Economista (in Spanish). Archived from the original on 5 May 2022. Retrieved 7 May 2022.
- ^ Camhaji, Elías (4 May 2022). "El Gobierno de Ciudad de México demanda a DNV, la empresa encargada de los peritajes de la Línea 12" [The Government of Mexico City Sues DNV, the Company Responsible for the Line 12 Investigations]. El País (in Spanish). Archived from the original on 5 May 2022. Retrieved 5 May 2022.
- ^ "Sheinbaum demandará a DNV por peritaje 'tendencioso y falso' del desplome de la Línea 12" [Sheinbaum Will Sue DNV for 'Tendentious and False' Investigation of the Line 12 Collapse]. Proceso (in Spanish). 4 May 2022. Archived from the original on 4 May 2022. Retrieved 5 May 2022.
- ^ Camhaji, Elías (11 May 2022). "El Gobierno de Sheinbaum hace público el informe de DNV que adelantó EL PAÍS sobre el colapso en la Línea 12" [The Sheinbaum Government Releases DNV Report on the Line 12 Collapse, Previously Leaked by El País]. El País (in Spanish). Archived from the original on 11 May 2022. Retrieved 11 May 2022.
- ^ Yaes, Brenda (5 May 2022). "Informe de DNV sobre L12 "nos sembró el mantenimiento", acusa Andrés Lajous" [DNV Report on Line 12 'Planted Maintenance Issues', Accuses Andrés Lajous]. Expansión (in Spanish). Archived from the original on 5 May 2022. Retrieved 5 May 2022.
- ^ Slater, Neil (11 May 2022). "Media statement regarding Mexico City Metro line investigation". DNV. Archived from the original on 8 December 2023. Retrieved 19 October 2024.
- ^ Buendía, Eduardo (6 May 2022). "¿Quién es Héctor Salomón, abogado de DNV acusado por Sheinbaum de trabajar para Peña Nieto?" [Who is Héctor Salomón, the DNV Lawyer Accused by Sheinbaum of Working for Peña Nieto?]. Milenio (in Spanish). Mexico City. Archived from the original on 7 May 2022. Retrieved 11 May 2022.
- ^ Zerega, Georgina; Camhaji, Elías; Manetto, Francesco (9 May 2022). "El peritaje final de DNV señala fallas en las inspecciones y el mantenimiento como causas concurrentes en la tragedia de la Línea 12" [DNV's Final Report Identifies Inspection and Maintenance Failures as Contributing Causes of the Line 12 Tragedy]. El País (in Spanish). Archived from the original on 11 May 2022. Retrieved 11 May 2022.
- ^ "El País revela el peritaje final de DNV a la Línea 12 del Metro; fallas en el mantenimiento, entre las causas del accidente" [El País Reveals DNV's Final Report on Line 12 of the Metro; Maintenance Failures Among the Causes of the Accident]. SDP Noticias (in Spanish). 9 May 2022. Archived from the original on 10 May 2022. Retrieved 11 May 2022.
- ^ "Colapso de Línea 12: Estas inconsistencias detectó el Gobierno de CDMX en el dictamen final de DNV" [Line 12 Collapse: These Inconsistencies Were Found by the Mexico City Government in DNV's Final Report]. El Financiero (in Spanish). 11 May 2022. Retrieved 11 May 2022.
- ^ "Sheinbaum busca nuevo peritaje sobre colapso en la Línea 12 con 'ingenieros de calidad'" [Sheinbaum Seeks New Investigation into Line 12 Collapse with 'Quality Engineers']. Proceso (in Spanish). 6 May 2022. Archived from the original on 9 May 2022. Retrieved 11 May 2022.
- ^ a b c El Universal (19 June 2021). "Metro CDMX: Línea 12 no puede reabrir; detectan más fallas" [Mexico City Metro: Line 12 cannot reopen; additional faults detected]. El Imparcial (in Spanish). Mexico City. Archived from the original on 20 June 2021. Retrieved 21 June 2021.
- ^ "Sheinbaum cuestiona intereses ocultos en revelación de NYT sobre L-12" [Sheinbaum questions hidden interests behind NYT's revelations regarding Line 12]. Forbes México (in Spanish). Mexico City. 13 June 2021. Archived from the original on 23 June 2021. Retrieved 20 June 2021.
- ^ Wong, Alma Paola; Vega, Carlos (14 June 2021). "Problemas en L12 del Metro, por falta notoria de mantenimiento en vías: Ebrard a NYT" [Ebrard attributes issues on Line 12 of the Metro to a significant lack of maintenance on the tracks, in response to the NYT] (in Spanish). Archived from the original on 24 June 2021. Retrieved 20 June 2021.
- ^ Paredes, Ariana (15 October 2021). "L12: los pernos Nelson, otra vez" [Line 12: Nelson Studs, Again]. El Universal (in Spanish). Mexico City. Archived from the original on 17 October 2021. Retrieved 18 October 2021.
- ^ "En L12, el colapso fue fundamentalmente por errores en construcción: Fiscalía capitalina" [In Line 12, the collapse was fundamentally due to construction errors: Mexico City Attorney General's Office]. El Universal (in Spanish). 14 October 2021. Archived from the original on 15 October 2021. Retrieved 18 October 2021.
- ^ "Third of required bolts missing from collapsed Mexico City metro section – study". Bnamericas. 10 January 2022. Archived from the original on 10 February 2022. Retrieved 10 February 2022.
- ^ "Another study finds maintenance errors at collapsed Mexico City metro line". Bnamericas. 24 January 2022. Archived from the original on 10 February 2022. Retrieved 10 February 2022.
- ^ Mandujano Tovar, Rocío (17 June 2021). "Colegio de Ingenieros Civiles de México detecta deficiencias en 32% de L12 del Metro CDMX" [The College of Civil Engineers of Mexico identifies deficiencies in 32% of Mexico City Metro Line 12]. Noticieros Televisa (in Spanish). Archived from the original on 19 June 2021. Retrieved 21 June 2021.
- ^ "Colegio de Ingenieros recomienda no reiniciar operaciones en L12; detecta fisuras y filtraciones" [The College of Engineers recommends against resuming operations on Line 12, citing detected fissures and leaks]. Animal Político (in Spanish). 17 June 2021. Archived from the original on 24 June 2021. Retrieved 23 June 2021.
- ^ "No se podrá abrir Línea 12 hasta reparar tramo colapsado: Colegio de Ingenieros Civiles" [Line 12 cannot be reopened until the collapsed section is repaired, according to the College of Civil Engineers]. Capital 21 (in Spanish). 17 June 2021. Archived from the original on 14 December 2024. Retrieved 15 February 2025.
- ^ "Para 2022 se terminará reconstrucción de Línea 12 del Metro: Sheinbaum" [Sheinbaum announced that the reconstruction of Line 12 of the Metro is expected to be completed by 2022]. Milenio (in Spanish). Mexico City. 8 December 2021. Archived from the original on 9 December 2021. Retrieved 17 December 2021.
- ^ Mora, Karla (13 May 2021). "Línea 12 del Metro: Perfilan plan para abrir tramo subterráneo" [Line 12 of the Metro: A plan is being developed to open the underground section.]. La Razón (in Spanish). Archived from the original on 24 June 2021. Retrieved 23 June 2021.
- ^ Zamarrón, Israel (18 June 2021). "Sheinbaum busca que ICA y Slim aporten dinero para rehabilitar Línea 12" [Sheinbaum seeks financial contributions from ICA and Slim to rehabilitate Line 12]. Forbes México (in Spanish). Mexico City. Archived from the original on 24 June 2021. Retrieved 23 June 2021.
- ^ Jiménez, Néstor; Martínez, Fabiola (23 June 2021). "Slim, con voluntad para apoyar reconstrucción de la L-12: AMLO" [Slim is willing to support the reconstruction of Line 12, according to AMLO]. La Jornada (in Spanish). Archived from the original on 23 June 2021. Retrieved 23 June 2021.
- ^ Pedro Domínguez (24 June 2021). "A más tardar en un año estará operando la Línea 12 del Metro de CdMx, dice AMLO" [AMLO states that Line 12 of the Metro in Mexico City will be operational within a year at the latest]. Milenio. Mexico City. Archived from the original on 27 June 2021. Retrieved 27 June 2021.
- ^ "Slim pagará reconstrucción del tramo colapsado de Línea 12, no le costará al pueblo, dice AMLO" [AMLO announces that Slim will cover the costs for the reconstruction of the collapsed section of Line 12, ensuring it won't be a burden on the public]. Animal Político (in Spanish). 30 June 2021. Archived from the original on 30 June 2021. Retrieved 30 June 2021.
- ^ García Soto, Salvador (30 June 2021). "Slim pagará, pero defiende la obra de L12" [Slim will cover the costs, but he defends the integrity of the Line 12 project]. El Universal (in Spanish). Archived from the original on 30 June 2021. Retrieved 30 June 2021.
- ^ "Carlos Slim Helú: la Línea 12, sin vicios de origen en su construcción" [Carlos Slim Helú: Line 12 was built without inherent flaws in its construction]. Expansión (in Spanish). 29 June 2021. Archived from the original on 30 June 2021. Retrieved 30 June 2021.
- ^ Argüelles, Efrén (16 February 2022). "Línea 12 del Metro: Inicia reconstrucción en zona cero tras desplome" [Metro Line 12: Reconstruction Begins at Ground Zero After Collapse]. Excélsior (in Spanish). Mexico City. Archived from the original on 17 February 2022. Retrieved 21 February 2022.
- ^ Corona, Salvador (7 March 2022). "Reconstruirán otro tramo de la parte elevada de la Línea 12" [Another Section of the Elevated Line 12 Will Be Reconstructed]. El Universal (in Spanish). Mexico City. Archived from the original on 7 March 2022. Retrieved 15 March 2022.
- ^ "Reconstrucción de la Línea 12 del Metro CDMX se realiza con acero del Aeropuerto de Texcoco" [Reconstruction of Mexico City's Line 12 Metro is Being Carried Out with Steel from the Texcoco Airport]. Infobae (in Spanish). 17 October 2022. Archived from the original on 28 October 2022. Retrieved 28 October 2022.
- ^ Jiménez, Adrián (13 October 2022). "Acero del aeropuerto de Texcoco se utiliza en reforzamiento de L12, confirma Sheinbaum" [Sheinbaum Confirms Use of Texcoco Airport Steel for Reinforcement of Line 12]. MVS Noticias (in Spanish). Archived from the original on 28 October 2022. Retrieved 28 October 2022.
- ^ Navarrete, Shelma (15 January 2023). "A 20 meses del desplome de la Línea 12, reabren tramo Mixcoac-Atlalilco" [20 Months After the Collapse of Line 12, the Mixcoac-Atlalilco Section Reopens]. Expansión (in Spanish). Archived from the original on 15 January 2023. Retrieved 15 January 2023.
- ^ "Metro Línea 12 reabrió tramo subterráneo; Sheinbaum recalcó que por 'eventos malintencionados' involucraron a la GN" [Metro Línea 12 reopened its underground section, with Sheinbaum emphasizing that the National Guard was involved due to "malicious events".]. Infobae (in Spanish). 15 January 2023. Archived from the original on 15 January 2023. Retrieved 15 January 2023.
- ^ Morán Breña, Carmen (16 January 2023). "Sheinbaum insiste en el sabotaje del metro y pone los "casos atípicos" en manos de la Fiscalía" [Sheinbaum insists on the sabotage of the metro and has handed over the "atypical cases" to the Prosecutor's Office]. El País. Archived from the original on 18 June 2024. Retrieved 19 October 2024.
- ^ "Reabren Línea 12 del Metro tramo Culhuacán a Periférico Oriente" [The section from Culhuacán to Periférico Oriente of Line 12 of the Metro has reopened]. unomásuno (in Spanish). 15 July 2023. Archived from the original on 16 July 2023. Retrieved 16 July 2023.
- ^ "Reapertura de la Línea 12 del Metro: ¿Qué estaciones abren, cuándo y a qué hora?" [Reopening of Metro Line 12: Which stations are opening, when, and at what time?]. El Financiero (in Spanish). 28 January 2024. Archived from the original on 28 January 2024. Retrieved 29 January 2024.
- ^ Rivera, José Antonio (22 June 2021). "Grupo Carso pierde 7,887 millones de pesos en la BMV desde la conferencia sobre Línea 12" [Grupo Carso has lost 7.887 billion pesos on the Mexican Stock Exchange since the press conference regarding Line 12]. El Economista (in Spanish). Archived from the original on 27 June 2021. Retrieved 27 June 2021.
- ^ Puga, Tláloc (30 June 2021). "Tras anunciar que rehabilitará tramo de la L12, Carso pierde 2 mil 734 mdp en dos días" [After announcing the rehabilitation of a section of Line 12, Carso lost 2.734 billion pesos in just two days]. El Universal (in Spanish). Archived from the original on 1 July 2021. Retrieved 5 July 2021.
- ^ García Soto, Salvador (9 September 2021). "DNV denuncia violación a sus investigaciones" [DNV reports a breach in its investigations]. El Universal (in Spanish). Archived from the original on 10 September 2021. Retrieved 10 September 2021.
- ^ "FGJCDMX investiga a 11 soldadores y 2 directivos por accidente de Línea 12 del Metro" [FGJCDMX investigates 11 welders and 2 executives for the Line 12 Metro accident]. Proceso (in Spanish). 11 August 2021. Archived from the original on 17 August 2021. Retrieved 10 September 2021.
- ^ Fuentes, David (18 October 2021). "Por L12, buscan imputar homicidio culposo, daños y lesiones a Horcasitas y otros 9: abogado" [For Line 12, they seek to charge Horcasitas and 9 others with manslaughter, damage, and injury: lawyer]. El Universal (in Spanish). Mexico City. Archived from the original on 18 October 2021. Retrieved 18 October 2021.
- ^ Trejo, Yeseline (18 October 2021). "Fiscalía CDMX presenta 10 denuncias por colapso de Línea 12" [Mexico City Attorney's Office files 10 complaints over Line 12 collapse]. Diario AS (in Spanish). Mexico City. Archived from the original on 18 October 2021. Retrieved 18 October 2021.
- ^ "¿Quién es Enrique Horcasitas, director del proyecto Metro del 2006 al 2012?" [Who is Enrique Horcasitas, the project director of the Metro from 2006 to 2012?]. SDP Noticias (in Spanish). Mexico City. 18 October 2021. Archived from the original on 18 October 2021. Retrieved 18 October 2021.
- ^ Hernández, Nelly (19 October 2021). "En la traducción de peritaje de L12 eliminaron el tema de mantenimiento: Abogado" [In the translation of the Line 12 report, the topic of maintenance was omitted: Lawyer]. Radio Fórmula (in Spanish). Archived from the original on 20 October 2021. Retrieved 19 October 2021.
- ^ "Imputan a diez exfuncionarios por caída de metro de México" [Ten former officials are charged in connection with the Mexico City Metro collapse]. Chicago Tribune. Mexico City. Associated Press. 6 December 2021. Archived from the original on 17 December 2021. Retrieved 17 December 2021.
- ^ "Carso destinará 800 millones de pesos a reparar la Línea 12" [Carso will allocate 800 million pesos to repair Line 12]. Expansión (in Spanish). 26 October 2021. Archived from the original on 27 October 2021. Retrieved 3 November 2021.
- ^ "Revelan que Carso subcontrató a empresa para fijar los pernos en la Línea 12 del Metro" [It has been revealed that Carso subcontracted a company to fix the studs on Line 12 of the Metro]. Aristegui Noticias (in Spanish). 3 November 2021. Archived from the original on 3 November 2021. Retrieved 3 November 2021.
- ^ a b Camhaji, Elías (31 January 2022). "Carlos Slim's company pays out thousands of dollars to Mexico City metro tragedy victims to prevent further lawsuits". El País. Translated by Kitson, Melissa. Archived from the original on 4 February 2022.
- ^ Vela, David Saúl (2 May 2022). "Colapso en Línea 12 del Metro: Difieren audiencia de imputación a Enrique a Horcasitas" [Collapse of Line 12 of the Metro: Hearing to charge Enrique Horcasitas postponed] (in Spanish). Archived from the original on 3 May 2022. Retrieved 5 May 2022.
- ^ "Línea 12 del Metro: Cicsa de Slim paga miles de pesos en acuerdos reparatorios a víctimas del colapso" [Line 12 of the Metro: Slim's Cicsa pays thousands of pesos in settlement agreements to victims of the collapse]. El Economista (in Spanish). 1 February 2022. Archived from the original on 3 February 2022. Retrieved 2 February 2022.
- ^ Pantoja, Sara (31 January 2022). "Empresa de Slim dará hasta 6 mdp a familias de fallecidos en Línea 12; no podrán demandar" [Slim's company will pay up to 6 million pesos to the families of those who died in Line 12; they will not be able to file lawsuits]. Proceso (in Spanish). Mexico City. Archived from the original on 1 February 2022. Retrieved 2 February 2022.
- ^ Pantoja, Sara (2 February 2022). "Fiscal llama a todas las víctimas de la Línea 12 a firmar el acuerdo con Slim" [Prosecutor calls on all victims of Line 12 to sign the agreement with Slim]. Proceso (in Spanish). Mexico City. Archived from the original on 3 February 2022. Retrieved 2 February 2022.
- ^ a b "Mexico president hits back at critics over metro crash". France 24. Mexico City. 6 May 2021. Archived from the original on 6 May 2021. Retrieved 6 May 2021.
Further reading
- "Línea 12 puede puede colapsar sin mantenimiento: TSO" [Line 12 can collapse without maintenance: TSO]. Forbes México (in Spanish). Mexico City. 7 April 2014.
- "Mexico City Government Reports Technical and Scientific Inconsistencies Found In Phase III Report Submitted by DNV on Metro Line 12". Government of Mexico City. 11 May 2022.
- Lagunas, Icela (November 2021). Línea 12: Crónica de una tragedia anunciada [Line 12: Chronicle of a tragedy foretold] (in Spanish). Planeta Group. ISBN 9786070781902.
- Zerega, Georgina (28 April 2022). "Un peritaje presentado por víctimas del desplome de la Línea 12 del metro apunta a fallas en el diseño, la construcción y el mantenimiento" [An expert report submitted by victims of the collapse of Metro Line 12 highlights flaws in design, construction and maintenance]. El País (in Spanish). The article includes a 26-minute video featuring Tomás Andrade Ramos, an architectural engineer, who explains the structure's composition and the factors that contributed to the collapse.
External links
- Line 12 openness website by the Government of Mexico City (in Spanish)
- DNV's technical report of the accident, published by the Government of Mexico City (in Spanish)